Client / Industry:
Hoffmann-La Roche AG / Pharma
Location / Country:
Basel / Switzerland
Project / Type / Year:
TRD-B97 / R&D / 2006 - 2011
Budget:
Sfr. 250 Mio. (Construction)
Service NIKBCON:
LEAD ELECTRICAL

Details:
NIKBCON is working as a subconsultant for M+W Process Industries GmbH and Lead ELECTRICAL for the KIWI AG  during all design and construction phases of the project. The new building is part of the future galenik research and technical development at Roche's headquarters in Basel and has a BGF of ~ 22,700 m² and a BGV of ~ 97,000 m³.  The electrical power capacity is ~ 3.6 MVA. The project is under construction at the moment and proposed to be finished by early 2011.
 


Client / Industry:
Bohringer-Ingelheim / Pharma
Location / Country:
Biberach / Germany
Project / Year:
> 300 Various / 2000 - 2012
Budget:
Various
Services NIKBCON:
ELECTR. DESIGN & CONSTRUCTION SERVICES
CLIENT REPRESENTATIVE

Details:
Since over 10 years we are working on ambitious projects for Boehringer-Ingelheim at their site in Biberach. Initially we were subconsultant for LSMW GmbH and part of the electrical design team that built G104, a state-of-the art Bio-Pharmaceutical plant with a floorspace of 25,000 m² on 10 storeys and an electrical capacity of 5 MW. Part of the design included midvoltage and lowvoltage switch gear, normal - standby - UPS power supply and distribution, a 160 kVA UPS system, fire alarm system, data and communication system, lighting & lighting control , air-locks, access control and CCTV systems. (Construction budget ~ $320m cdn)

Since this time, we have managed and coordinated more than 300 small to large scale projects as Client representative, not only in the electrical field, but also in the mechanical (HVAC), heating and plumbing - in cleanroom environment as well as for research & development, admin and other areas. Follwing are some examples, where we accompanied the project from SD through construction and commissioning:

  • D123 new Admin
  • H122 new R & D building
  • G71  retrofit of the complete building
  • G84   new Restaurant for 2,200 employees
  • F113  retrofit of Coaters 2, 4, 5, & 6

Client:
Schwarz Pharma GmbH
Location / Country:
Zwickau / Germany
Project / Type / Year:
Research & Prod. Facility / 2006-2007
Budget:
estimated € 300 T (Electrical Construction)
Services NIKBCON:
ELECTR. DESIGN & CONSTRUCTION SERVICES

Details:
With the CARPUS AG as the prime consultant, NIKBCON provided the  complete electrical  design and construction services of the expansion and renovation of the existing research and production facility of the Schwarz Pharma GmbH .

 

Client:
ALAPIS
Location / Country:
Athens / Greece
Project / Type / Year:
Revamp of production building / 2008 - 2009
Budget:
estimated € 405 T (Electrical Construction)
Service NIKBCON:
ELECTR. BASIC DESIGN (Phase 1 & 2)

Details:
Renovation and upgrade of an existing production facility for oral dosage forms and ointments. NIKBCON as subconsultant for LSMW GmbH was responsible for the complete electrical basic design, BD report, and specifications. Drawings and documents were produced and submitted to several general contractors in order for them to provide a design-built fee proposal. NIKBCON also assisted in the evaluation of the bidders and accompanied the selection process to award the successful bidder.


Client
SPECIFAR Pharmaceuticals
Location / Country:
Athens / Greece
Project / Type / Year:
Manufacturing Plant / 2008 - 2009 & 2012
Budget:
estimated $ 5.8 Mio. (Electrical Construction)
Service NIKBCON:
ELECTR. BASIC & DETAIL DESIGN

Details:
At its head-quarter in Athens, Specifar produces tablets, liquids and semisolids in a cleanroom environment. The proposed new manufacturing plant has a BGF of ~ 22,300 m², and  will accommodate up to 16 * tablet packaging units and a five (5) storey warehouse. 4 * 1,600 kVA xfrm (20 kV - 400V) provide power to the new facility. An additional 900 kW Diesel Generator and a 60 kW UPS  supply back-up power in case of a power outage. As subconsultant of LSMW GmbH, NIKBCON was responsible for the complete design of the electrical system and distribution, including Fire Alarm system, air-lock controls, time - and access control, CCTV system, communication system, emergency and EXIT lighting, lighting and lighting control, lightning protection. NIKBCON also provided an order-of-magnitude cost estimation for the electrical systems.


Client:
Merck KgaA
Location / Country:
Jena / Germany
Project / Type / Year:
New Biofab Production Facility / 2003
Budget:
estimated € 4.01 Mio. (Electrical Construction)
Service NIKBCON:
ELECTR. BASIC DESIGN

Details:
The Merck KgaA wanted to build a new bio-pharmaceutical production plant in Jena. NIKBCON as subconsultant for LSMW GmbH was responsible for the complete electrical basic design of the following systems: Fire Alarm, Communication, Intercom, Video surveillance, Paging - and Speaker system, Intrusion, Time control and access systems.